APM in Practice: How an Automation Project Is Executed From Start to Finish

An illustrative case of APM applied to a purchase approval process: how the business case is built, how execution is controlled, and how real ROI is measured against the promised one, with a team that ends up leading the process instead of holding it up.

Deciding to automate is rarely the problem. The problem is what happens between the decision and the result: how much is invested, what's expected, and who responds when something doesn't go as planned.

To show it, let's follow an illustrative case built with typical figures from the diagnostics we run: a services company in Colombia, between 51 and 200 people, that wants to automate purchase order approvals.

The process: 120 requests a month. Each one takes an average of 90 minutes of work spread across six people, from the requester to the finance manager. Emails, reminders, a shared spreadsheet, and approvals that sit waiting when the approver is traveling.

This is what that same process looks like as an automation project with ROI, from start to finish.


Before: Guesswork


Before APM, the conversation sounded like this: "this takes up a lot of our time, let's automate it." Nobody knew how much time, how much it cost, or which part of the process was worth touching.

The first step was turning the feeling into numbers. 120 cases at 1.5 hours each is 180 hours a month, the equivalent of 1.07 full-time people. With an average salary of COP 3.5 million plus benefits, an hour of work costs about COP 31,900. The process consumes roughly COP 5.7 million a month.

But that wasn't the most useful number. The most useful finding was where the time went: 60% of the waiting wasn't in reviewing orders, it was in chasing approvals. And only one person, the purchasing coordinator, knew the status of each request. If she was out, the process stopped.

With that, the business case stopped being a hunch: 70% of the process automatable, projected savings of COP 4 million a month, a first-year investment of COP 30 million (implementation plus license), and an estimated payback of 6 months. Projected first-year ROI: 61%.

What would not be automated was also written down: orders above a certain amount and purchases from new suppliers would still go through human judgment. That decision is worth as much as the previous one, and it answers the same questions that define ROI before automating.


During: Control


In a traditional project, implementation is a black box: requirements are handed over and everyone waits for the go-live date. With APM, execution has review points with business criteria, not just technical ones.

Three decisions shaped this phase.

→ The order. The team didn't start with the request form, which was the most visible part. It started with the approval routes, which is where the process stalled. It's the logic of deciding what to automate first, and what not to.

→ The exceptions. Every case that didn't fit a rule got an owner and a criterion: who decides, with what information, and how fast.

→ The role of people. The purchasing coordinator stopped being the place where every request's status lived. She moved on to leading the process: she monitors the dashboard, decides the exceptions, and proposes adjustments. The process no longer stops when she's out, and her judgment carries more weight than before, because now it's applied where it matters.

⚠️ In week five, a wrong assumption surfaced: almost a third of orders arrived with incomplete data, and the flow kept sending them back. With an improvised method, that would have been fixed with a patch. With APM, it was logged as a finding, the form's entry rule was adjusted, and the business case was updated with the real data.

That kind of control is what makes it possible to run the automation without depending on whoever built it.


After: ROI Measured


After three months of operation, the first measurement was done with real data, not the business case figures.

Time per request dropped from 90 to 34 minutes. The projection said 27. The process automated 62% of the work, not 70%: orders with incomplete data and some supplier exceptions still required intervention.

With that real figure, monthly savings came to COP 3.56 million, first-year ROI to 43%, and payback to just over 7 months.

💰 Less than projected, and still an investment that pays for itself before the year is out. The gap between the promised 61% and the real 43% isn't a failure. It's the information that makes the next calculation more precise, and it's exactly the point of measuring the real ROI, not the promised one.

The measurement also showed something no projection included: approvals that used to take up to five days are now resolved in less than one. Suppliers get answers on time, and the purchasing team stopped spending its mornings chasing signatures. That time now goes into negotiating better terms, something there was never room for before.

With the real data, the second cycle already has a clear goal: fix data capture at the source to bring the process closer to 70% automatable. That turns the project into a system that learns, not a one-time delivery.


Why Decisions Are No Longer Made Blind


What changed at this company wasn't just the purchasing process. It was the way decisions get made.

Before, every automation was justified by urgency or enthusiasm. Now there's a method: measure before, control during, verify after. Every project leaves real data that improves the estimate for the next one.

🌀 And people didn't leave the process. They changed their place in it: they stopped holding it up by hand and moved on to managing it. Technology runs the repetitive work. People think, decide, and improve.

That's the fundamental difference between APM and traditional automation: one delivers tools, the other builds the capacity to keep deciding well.

An automation that isn't measured before, during, and after isn't a decision, it's a bet with a budget.


If you can't say today how much your last automation returned, start there.

📌 Write to me and let's talk about a process.

Share this article with someone who might be interested in learning about this.

Frequently asked questions

How is an automation project executed with APM?

In three phases with business criteria. Before: the process is measured (cases, time, cost, people involved) and the business case is built, including what will not be automated. During: execution is controlled with review points, exceptions get owners, and the team's role is redefined. After: real ROI is measured with operating data and the next cycle is decided.

How is the payback of an automation calculated?

By dividing the implementation investment by the net monthly savings (savings generated minus the monthly cost of the tool). In the illustrative case, an implementation of COP 18.6 million with net savings of about COP 3 million a month projected a payback of 6 months. With real data it came to just over 7.

What happens if real ROI is lower than projected?

It's recorded as information, not hidden as a failure. The gap shows which assumption was wrong (incomplete data, unanticipated exceptions, different volume) and defines the goal of the next cycle. In the case, ROI went from a projected 61% to a real 43%, and the investment still paid for itself within the year.

How does the team's role change in an APM project?

People stop holding the process up by hand and move on to leading it. In the case, the purchasing coordinator stopped being the only one who knew the status of each request: she now monitors the dashboard, decides exceptions, and proposes adjustments. The process no longer stops when she's out, and her judgment is applied where it adds the most.

+1- 407 9907657
mmp@timeautomationagency.com

NEVADA, United States

Fax : +1 775-375-4140

Shipping Address: BWH1-232-2 4104 L B MCLEOD ORLANDO, FL 32811-5650 United States

Identify the automation ROI for your FIRST process:

Or subscribe to statistics on real-world automation cases, featuring ROI and measurements of time saved:

Follow

  • Instagram
  • Linkedin

© 2025

bottom of page